A406 Bounds Green
We are creating a dual-carriageway that will help cut out rat-running (cut-through) traffic in residential streets, increase safety and benefit the local environment for everyone.
Other benefits include improved journey time reliability, reduced congestion, better facilities for cyclists, and traffic encouraged back onto the main carriageway, away from residential roads.
The main construction work started in May 2010 and is expected to take up to two years to complete.
Construction milestones
| Date | Milestone |
|---|---|
| Autumn 2011 | Powys Lane/A406 Bowes Road junction has re-opened to all traffic |
| Autumn 2011 | Completion of shared cycle/footway A406 North Circular |
| Winter 2011 | Completion of tree planting and scheme landscaping |
| Winter 2011/12 | Resurfacing complete |
| Spring 2012 | Completion of works at all major junctions |
| Spring 2012 | Construction complete |
Crichel Down notices
Crichel Down notice - houses (PDF 20KB)Crichel Down notice - demolished properties (PDF 15KB)
Contact us
If you'd like to be kept informed of scheme developments.
Telephone: 0845 305 1234 (24 hours a day)
Email: boundsgreen@tfl.gov.uk
Post: London Streets
Customer Services
4th Floor Zone G7 Palestra
197 Blackfriars Road
London SE1 8NJ
Transport for London